BOQ and specifications

How to prepare a furniture BOQ

A practical structure for turning furniture design information into a document that can be priced, compared, ordered and tracked.

9 minute read

Reviewed by Zoon Interior’s architectural team in Istanbul.

About the studio

Short answer

A furniture BOQ is the control table for scope, quantity and price.

A furniture bill of quantities lists every item with a unique code, description, location, quantity, unit and specification reference. During procurement it also records supplier, unit rate, totals, inclusions, status and delivery information. A strong BOQ does not replace drawings or specifications; it connects them so bidders price the same scope and the project team can track each item through approval and delivery.

01

What a furniture BOQ is for

The BOQ creates a common item structure for design, commercial and delivery teams. Designers use it to confirm scope and quantities. Bidders use it to price. Procurement teams use it to compare offers and place orders. Production and site teams use the same codes to inspect, pack, receive and install.

If the BOQ is only a price list, it becomes disconnected from the project. If it tries to contain every fabrication detail, it becomes unreadable and difficult to revise. Keep the table concise and link each row to the controlled specification and drawing information.

  • One unique item code used across all documents
  • Clear quantity and location basis
  • Enough description to identify the pricing scope
  • References to drawings, specifications and finishes
  • Commercial and status fields appropriate to the current stage

02

Essential BOQ columns

Start with stable identification fields, then add commercial and tracking fields as the project develops. Do not make one cell carry several meanings. For example, keep room, floor and quantity separate so totals can be checked and filtered.

The units should fit the item. Loose chairs are counted as each; curtains may be measured by set or area depending on the package; built-in joinery may be priced by item, linear length or defined assembly. State the basis rather than leaving bidders to choose.

FieldPurposeExample
Item codeStable reference across documentsCHR-01
LocationRoom, zone or room typeGuest room — Type A
DescriptionPlain-language item nameUpholstered lounge chair
Quantity / unitMeasured procurement amount24 / each
Specification referenceLink to controlled detailSPEC-CHR-01 Rev B
Supplier / rate / totalCommercial comparisonBidder entry
Status / required dateApproval and delivery trackingSample approved / 15 Oct

03

Example furniture BOQ structure

The example below shows the level of information suitable for an early tender. Expand the commercial fields after bids arrive, and keep detailed performance and fabrication notes in the linked specification. Use separate rows when the same design has a different size, finish or price.

For repeated hospitality or residential units, create a room-type quantity matrix and reconcile it with the overall BOQ. This makes it easier to detect whether the item quantity comes from the number of rooms, an area schedule or a manual allowance.

CodeItemLocationQtyUnitSpecification / scope
CHR-01Dining chairRestaurant48eachTimber frame, upholstered seat; finish sample and performance evidence required
TBL-02Dining tableRestaurant12eachCustom top and metal base; shop drawing and first-off approval required
BNQ-01Fixed banquetteRestaurant wall18linear mSite-measured joinery; coordinate wall, floor and power interfaces
LTG-03Decorative pendantBar6eachFixture supply; confirm driver, suspension and electrical-package boundary

04

Set pricing rules before issuing the BOQ

A bidder needs to know what the rate includes. State whether pricing includes shop drawings, samples, prototypes, hardware, packaging, factory inspection support, delivery, installation, taxes and spare materials. Ask bidders to list exclusions and alternatives separately rather than embedding assumptions in notes.

Use one currency basis and identify exchange-rate assumptions where comparison spans currencies. Separate optional items and provisional allowances. Check arithmetic, quantities and duplicate codes before issue, then lock the revision so every response can be traced to the same version.

  • Price basis and currency
  • Included design-development and approval work
  • Packaging, freight, customs and installation boundary
  • Taxes, duties and insurance treatment
  • Lead time, validity, payment terms and warranty
  • Required breakdown for alternatives and exclusions

05

Control revisions and changes

Furniture quantities and specifications evolve. Add a revision, issue date and status to the BOQ; archive previous issues rather than overwriting them. When a row changes after order, record whether it is a design development, variation, cancellation or approved substitution.

A change log should show the previous value, new value, reason, cost effect, programme effect and approver. Without this link, the BOQ total may change while the project team cannot explain why.

  1. 01Issue a dated baseline for pricing.
  2. 02Answer bidder questions through a controlled clarification.
  3. 03Publish a revised BOQ when scope changes materially.
  4. 04Freeze the order revision and reference it in the purchase order.
  5. 05Track post-order changes in a separate authorised log.

06

Check the BOQ before it goes to market

Review the table from three perspectives. A designer should confirm that the item and specification express the intended result. A commercial reviewer should confirm that quantities and pricing rules allow a fair comparison. A delivery reviewer should confirm that the item can be packaged, shipped, received and installed within the stated scope.

Finally, test several rows end to end. Can you move from the item code to its location, drawing, finish, quantity, price and approval record without guessing? If not, fix the information chain before requesting final quotations.

  • No duplicate or missing item codes
  • Quantities reconcile with plans and room schedules
  • Every row has a clear specification or drawing reference
  • Bidder input cells and client information are visibly separated
  • Commercial inclusions and exclusions are explicit
  • Revision, status and issue purpose are visible

07

Frequently asked questions

What does BOQ mean in furniture procurement?

BOQ means bill of quantities. In furniture procurement it is an itemised schedule that identifies what must be supplied, where it is used, how much is required and how the scope will be priced and tracked.

Is a BOQ the same as a furniture specification?

No. The BOQ controls item identity, quantity and commercial tracking. The specification describes materials, construction, finishes, performance and approval requirements. They should reference each other.

Should images be placed inside the BOQ?

A thumbnail can help identification, but controlled reference images and drawings are often clearer in a separate specification sheet. Avoid large embedded files that make the BOQ difficult to filter, issue and revise.

Who should prepare the furniture BOQ?

The designer or furniture specialist commonly prepares the design and quantity basis, while the cost or procurement lead adds commercial fields and checks pricing rules. One named owner should control the issued document.

Furniture scope

We can review available drawings and schedules, identify missing decisions and help turn the furniture brief into a coordinated procurement scope.

Need a clearer package before approaching manufacturers?